Milestone Summary For Project | |||||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | WESTERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | UKNI DEEP OC. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
2 | Rehabilitation & resettlement | 0 | 4/2020 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 30 | On going | No | |
3 | Production Phasing (coal) | 0 | 4/2019 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 87 | On going | No | |
4 | Capital Expenditure (Rs 318.14 Cr) | 0 | 4/2019 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No |