Milestone Summary For Project | |||||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | NORTHERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | BLOCK-B EXPANSION OPENCAST PROJECT. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1 | Sanction of Recast EPR | 0 | 11/2018 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes | NCL |
4 | Possession of Non-forest land | 0 | 10/2019 | 3/2023 | 0/0 | 3/2024 | 0/0 | No | / | 0 | Completed | Yes | NCL |
5 | R & R | 0 | 10/2019 | 3/2023 | 0/0 | 3/2025 | 0/0 | No | / | 0 | Completed | Yes | NCL |
6 | Commissioning of 4.0 Incremental CHP | 0 | 4/2020 | 9/2022 | 0/0 | 3/2024 | 0/0 | No | / | 0 | Completed | Yes | NCL |