Milestone Summary For Project | |||||||||||||
Sector Name : | COAL. | ||||||||||||
Agency Name : | NORTHERN COAL FIELDS LIMITED. | ||||||||||||
Project Name : | BLOCK-B EXPANSION OPENCAST PROJECT. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
2 | Forestry Clearance (FC) | 0 | 10/2019 | 9/2021 | 0/0 | 9/2024 | 0/0 | No | / | 0 | On going | Yes | MoEF & CC |
3 | Environmental Clearance (EC) | 0 | 1/2020 | 3/2022 | 0/0 | 12/2024 | 0/0 | No | / | 0 | On going | Yes | MoEF & CC |
7 | Procurement of HEMM | 0 | 4/2022 | 3/2023 | 0/0 | 3/2025 | 0/0 | No | / | 0 | On going | Yes | NCL |