Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1 | NIT-FPSO | 0 | 5/2018 | 5/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
10 | TECHNICAL BID OPENING-CPP-LQUP | 0 | 2/2017 | 2/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
11 | NOTICE OF AWARD-CPP-LQUP | 0 | 3/2017 | 3/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
13 | NIT-DRILLING | 0 | 9/2016 | 9/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
14. | TECHNICAL BID OPENING-DRILLING | 0 | 12/2016 | 12/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
15 | NOTICE OF AWARD-DRILLING | 0 | 2/2017 | 2/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
17 | NIT- SURF SPS | 0 | 11/2016 | 11/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
18 | TECHNICLA BID OPENING- SURF SPS | 0 | 2/2018 | 2/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
19 | NOTIFICATION OF AWARD | 0 | 9/2018 | 9/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
2 | TECHNICAL BID OPENING-FPSO | 0 | 10/2018 | 10/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
3 | NOTICE OF AWARD-FPSO | 0 | 11/2018 | 11/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
4 | Completion -FPSO | 0 | 3/2021 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
4 | Completion -FPSO | 0 | 3/2021 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | |
5 | NIT-ONSHORE MEG | 0 | 11/2016 | 11/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
6 | TECHNICAL BID OPENING-ONSHORE MEG | 0 | 5/2018 | 5/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
7 | NOTICE OF AWARD-ONSHORE MEG | 0 | 5/2017 | 5/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |
9 | NIT-CPP-LQUP | 0 | 11/2016 | 11/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | OFFSHORE ENGG SERVICE (ONGC) |