Milestone Summary For Project | |||||||||||||
Sector Name : | PETROLEUM. | ||||||||||||
Agency Name : | INDIAN OIL CORPORATION LIMITED. | ||||||||||||
Project Name : | ENNORE THIRUVALLUR BENGALURU PUDUCHERRY NAGAPATTINAM MADURAITUTICORIN GAS PIPELINE. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |