Milestone Summary For Project
Sector Name : PETROLEUM.
Agency Name : GAS AUTHORITY OF INDIA LIMITED.
Project Name : KOCHI-KOOTTANAD-BANGALORE-MANGALORE PIPELINE PHASE-II.

Milestone

CodeMilestoneCost Associated with Milestones in (INR)Original Start (mm/yyyy)Original End (mm/yyyy)Revised Start (mm/yyyy)Revised End (mm/yyyy)Actual Completion (mm/yyyy)MOU StatusMOU Traget (mm/yyyy)% AchievedStatusCriticalRemarks
001Tendering Pipeline Laying Work02/20172/2017//0/0No/CompletedNo
002Ordering Pipeline Laying Work08/20178/2019//0/0No/CompletedNo
003Submission of allcrossings and statutory permissions012/201712/20170/00/00/0No/0CompletedNo
004Pipeline Laying Progress-25% 012/201712/20170/00/00/0No/0CompletedNo
005Pipeline Laying Progress-50%05/20185/20180/00/00/0No/0CompletedNo
006Pipeline Laying Progress-75%09/20189/20180/00/00/0No/0CompletedNo
007Receipt of allCrossings and statutory permissions06/20186/20180/00/00/0No/0CompletedNo
008Opening of entire ROU010/201810/20180/00/00/0No/0CompletedNo
009Pipeline Laying Progress -100%09/20199/20190/00/00/0No/0CompletedNo
010Mechanical Completion & Pipeline preservation03/20203/20200/00/00/0No/0CompletedNo
011Tendering - Coated & Bare Line Pipe-109/20179/2017//0/0No/CompletedNo
012Start of RoU Opening activities03/20183/20180/00/00/0No/0CompletedNo
013Tendering - Pipeline Laying Works-1011/201711/20170/00/00/0No/0CompletedNo
014Ordering - Coated & Bare Line Pipe -1012/201712/20170/00/00/0No/0CompletedNo
015Application forall crossings and statutory permissions 103/20183/20180/00/00/0No/0CompletedNo
016Ordering Pipeline Laying Works-105/20185/20180/00/00/0No/0CompletedNo
017Start of Delivery of Line pipe-104/20184/20180/00/00/0No/0CompletedNo
018Pipeline Laying Progress Section-1-25%08/20198/20190/00/00/0No/0CompletedNo
019Delivery complete - Coated & Bare Line Pipe -109/20199/20190/00/00/0No/0CompletedNo
020Pipeline Laying Progress Section-1-50%02/20192/20190/00/00/0No/0CompletedNo
021Pipeline Laying Progress Section-1-75%012/201912/20190/00/00/0No/0CompletedNo
022Receipt of allCrossingsand statutory permissions011/201911/20190/00/00/0No/0CompletedNo
023Completion of ROU Opening activities012/201912/20190/00/00/0No/0CompletedNo
024Pipeline Laying Progress Section-1 -100%02/20202/20200/00/00/0No/0CompletedNo
025Mechanical Completion & Pipeline preservation03/20203/20200/00/00/0No/0CompletedNo
026Meeting of Expert Committee011/201711/20170/00/00/0No/0CompletedNo
027Final reportfrom Expert Committee02/20182/20180/00/00/0No/0CompletedNo
028Tendering - Coated & Bare Line Pipe-203/20183/20180/00/00/0No/0CompletedNo
029Start of RoU Opening activities04/20184/20180/00/00/0No/0CompletedNo
030Tendering - Pipeline Laying Works-206/20186/20180/00/00/0No/0CompletedNo
031Ordering - Coated & Bare Line Pipe -209/20189/20180/00/00/0No/0CompletedNo
032Application forall crossings and statutory permissions-2012/201812/20180/00/00/0No/0CompletedNo
033Ordering Pipeline Laying Works-2012/201812/20180/00/00/0No/0CompletedNo
034Start of Delivery of Line pipe-204/20194/20190/00/00/0No/0CompletedNo
035Pipeline Laying Progress Section-2-25%08/20198/20190/00/00/0No/0CompletedNo
036Delivery complete - Coated & Bare Line Pipe -209/20199/20190/00/00/0No/0CompletedNo
037Pipeline Laying Progress Section-2 -50%012/201912/20190/00/00/0No/0CompletedNo
038Pipeline Laying Progress Section-2 -75%03/20203/20200/00/00/0No/0CompletedNo
039Receipt of allCrossings and statutory permissions06/20206/20200/00/00/0No/0CompletedNo
040Competetion of ROU Opening activities06/20206/20200/00/00/0No/0CompletedNo
041Pipeline Laying Progress Section-2 -100%08/20208/20200/00/00/0No/0CompletedNo

  Back