Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
001 | Tendering Pipeline Laying Work | 0 | 2/2017 | 2/2017 | / | / | 0/0 | No | / | | Completed | No | |
002 | Ordering Pipeline Laying Work | 0 | 8/2017 | 8/2019 | / | / | 0/0 | No | / | | Completed | No | |
003 | Submission of allcrossings and statutory permissions | 0 | 12/2017 | 12/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
004 | Pipeline Laying Progress-25% | 0 | 12/2017 | 12/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
005 | Pipeline Laying Progress-50% | 0 | 5/2018 | 5/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
006 | Pipeline Laying Progress-75% | 0 | 9/2018 | 9/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
007 | Receipt of allCrossings and statutory permissions | 0 | 6/2018 | 6/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
008 | Opening of entire ROU | 0 | 10/2018 | 10/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
009 | Pipeline Laying Progress -100% | 0 | 9/2019 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
010 | Mechanical Completion & Pipeline preservation | 0 | 3/2020 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
011 | Tendering - Coated & Bare Line Pipe-1 | 0 | 9/2017 | 9/2017 | / | / | 0/0 | No | / | | Completed | No | |
012 | Start of RoU Opening activities | 0 | 3/2018 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
013 | Tendering - Pipeline Laying Works-1 | 0 | 11/2017 | 11/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
014 | Ordering - Coated & Bare Line Pipe -1 | 0 | 12/2017 | 12/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
015 | Application forall crossings and statutory permissions 1 | 0 | 3/2018 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
016 | Ordering Pipeline Laying Works-1 | 0 | 5/2018 | 5/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
017 | Start of Delivery of Line pipe-1 | 0 | 4/2018 | 4/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
018 | Pipeline Laying Progress Section-1-25% | 0 | 8/2019 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
019 | Delivery complete - Coated & Bare Line Pipe -1 | 0 | 9/2019 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
020 | Pipeline Laying Progress Section-1-50% | 0 | 2/2019 | 2/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
021 | Pipeline Laying Progress Section-1-75% | 0 | 12/2019 | 12/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
022 | Receipt of allCrossingsand statutory permissions | 0 | 11/2019 | 11/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
023 | Completion of ROU Opening activities | 0 | 12/2019 | 12/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
024 | Pipeline Laying Progress Section-1 -100% | 0 | 2/2020 | 2/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
025 | Mechanical Completion & Pipeline preservation | 0 | 3/2020 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
026 | Meeting of Expert Committee | 0 | 11/2017 | 11/2017 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
027 | Final reportfrom Expert Committee | 0 | 2/2018 | 2/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
028 | Tendering - Coated & Bare Line Pipe-2 | 0 | 3/2018 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
029 | Start of RoU Opening activities | 0 | 4/2018 | 4/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
030 | Tendering - Pipeline Laying Works-2 | 0 | 6/2018 | 6/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
031 | Ordering - Coated & Bare Line Pipe -2 | 0 | 9/2018 | 9/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
032 | Application forall crossings and statutory permissions-2 | 0 | 12/2018 | 12/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
033 | Ordering Pipeline Laying Works-2 | 0 | 12/2018 | 12/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
034 | Start of Delivery of Line pipe-2 | 0 | 4/2019 | 4/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
035 | Pipeline Laying Progress Section-2-25% | 0 | 8/2019 | 8/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
036 | Delivery complete - Coated & Bare Line Pipe -2 | 0 | 9/2019 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
037 | Pipeline Laying Progress Section-2 -50% | 0 | 12/2019 | 12/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
038 | Pipeline Laying Progress Section-2 -75% | 0 | 3/2020 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
039 | Receipt of allCrossings and statutory permissions | 0 | 6/2020 | 6/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
040 | Competetion of ROU Opening activities | 0 | 6/2020 | 6/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |
041 | Pipeline Laying Progress Section-2 -100% | 0 | 8/2020 | 8/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | |