Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1 | land acqusition | 0 | 3/2009 | 3/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | Taml naduState Government |
1 | land acqusition | 0 | 3/2009 | 3/2012 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | Yes | Taml naduState Government |
3 | Ballast Collection | 0 | 3/2014 | 3/2015 | / | / | 0/0 | Yes | 3/2016 | 100 | Completed | No | |
4 | Track Linking | 0 | 3/2011 | 6/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | Delayed due to land acqustion by Tamilnadu Government |
4 | Track Linking | 0 | 3/2011 | 6/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | Delayed due to land acqustion by Tamilnadu Government |