Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | SOUTH CENTRAL RAILWAY. | ||||||||||||
Project Name : | MANOHARABAD-KOTHPALL NEW LINE(SCR). |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
MK1 | Tenders between Manoharabad and Gajwel | 0 | 8/2016 | 12/2016 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | Yes |