Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1.1 | Acquisition of Land in RRU- Jora Section of Morena District | 0 | 5/2017 | 12/2019 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | MP State Govt. (Collector, Morena) |
1.2 | Acquisition of land between Jora - SBL section of Morena Distric | 0 | 5/2017 | 8/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | MP state Govt. (Collector Morena) |
1.3 | Transfer of land between SBL- SOE section of Sheopur Distt | 0 | 12/2017 | 12/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | M.P. State GOvt Collector Sheopur |
2.1 | Execution of E/Work between BLNR - RRU section | 0 | 1/2019 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | Deputhy Chief Engineer Construction Gwalior |