Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | SOUTH WESTERN RAILWAY. | ||||||||||||
Project Name : | RAYADURGA-TUMKUR NL. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
01 | Rayadurga-Tumkur (part Rayadurga-Kalyanadurga 40 km) | 387.30 | 2/2012 | 2/2017 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | South Western Railway |
02 | Rayadurga-Tumkur (part Kalyanadurga-Kadaridevarapalli 21 km) | 222.70 | 1/2015 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | South Western Railway |