Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | SOUTH CENTRAL RAILWAY. | ||||||||||||
Project Name : | NADIKUDE-SRI KALAHASTI. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
NS1 | TENDERS FOR PHASE-I | 0 | 12/2014 | 7/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No |