Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | WEST CENTRAL RAILWAY. | ||||||||||||
Project Name : | KATNI - SINGRAULI DOUBLING PROJECT. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
KM01 | Interaction with WC railway and submission of draft MOU to west central Railway | 0 | 6/2016 | 8/2016 | / | / | 0/0 | Yes | 3/2016 | 100 | Completed | No | IRCON and West Central Railway |