Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | SOUTH EAST CENTRAL RAILWAY. | ||||||||||||
Project Name : | RAJNANDGAON - NAGPUR - 3RD LINE (SECR). |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
SECRRN12 | Commissioning of Kanhan-Kalumna | 0 | 11/2018 | 3/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No |