Milestone Summary For Project | |||||||||||||
Sector Name : | RAILWAYS. | ||||||||||||
Agency Name : | NORTH CENTRAL RAILWAY. | ||||||||||||
Project Name : | JHANSI BINA DOUBLING. |
Milestone |
Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
BJA-LAR | JHS BINA IIIrd line:("Bijrautha Lalitpur 29 km") | 3800000000 | 12/2016 | 10/2020 | 3/2017 | 5/2022 | 0/0 | No | / | 100 | Completed | Yes | Dy CE Jhansi Unit |
JHS-BAB | JHS BINA III line 152 km - ("Jhansi Babina-25.35 km") | 3320000000 | 12/2016 | 1/2020 | 12/2016 | 7/2021 | 0/0 | No | / | 100 | Completed | Yes | Dy CE Jhansi Unit |