Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
JLN-MXS | JHS BINA IIIrd line :("Jakhlaun-Mohasa-20 km") | 0 | 12/2016 | 10/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | Dy CE Jhansi |
LAR-JLN | JHS BINA IIIrd line :("Lalitpur-Jakhlaun-16.5 km") | 0 | 12/2016 | 10/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | Dy CE Jhansi unit |
MTA-BJA | JHS BINA IIIrd line:(Matatila-bijarautha:16 km | 0 | 12/2016 | 1/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | Dy CE Jhansi Unit |
MXS-AGD | JHS BINA IIIrd line :(Mohasa-Agasod-18 km) | 0 | 12/2016 | 1/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | Yes | Dy CE Jhansi |